截至2025年8月13日,法国北部Gravelines核电站因大量水母涌入海水过滤冷却系统,被迫部分关闭多个反应堆机组1。该电站位于上法兰西大区敦刻尔克与加来之间,由法国电力公司(EDF)负责运营1。
Gravelines核电站共配备六个机组,每个机组的发电能力均为900兆瓦1。受此次水母问题影响,该电站六个机组中有多个出现停机或降功率运行情况1。其中,第三机组自8月10日起因相同问题关闭,该机组此前曾于8月18日重新并网1。同时,第一和第二机组也已采取预防性措施降功率运行1。
这已是该核电站继去年8月之后再次遭遇水母引发的停机问题1。历史上,2011年苏格兰Torness电站与2013年瑞典Oskarshamn电站也曾发生过类似的水母堵塞事件1。
On August 13, 2025, the Gravelines nuclear power plant in northern France was forced to partially shut down multiple reactor units after a massive influx of jellyfish clogged the seawater filtration cooling system 1. Operated by Électricité de France (EDF), the facility is located in the Hauts-de-France region between Dunkirk and Calais 1.
The plant comprises six reactor units, each with a power generation capacity of 900 megawatts 1. According to EDF, the third unit has been shut down since August 10 due to the jellyfish issue and was reconnected to the grid on August 18 1. Additionally, the first and second units are operating at reduced power as a preventive measure 1.
This marks the second time the Gravelines facility has faced such a jellyfish problem, having previously experienced a similar shutdown in August of last year 1. Jellyfish disruptions at nuclear facilities are not unprecedented, as similar incidents occurred at the Torness plant in Scotland in 2011 and the Oskarshamn plant in Sweden in 2013 1.