NSW道路部长詹妮·艾奇逊周五在预算估算委员会上承认,悉尼南部M6地下高速公路项目没有完工日期1。这条4公里的Arncliffe至Kogarah段项目原定2028年末开放,但在承包商与政府的纠纷以及多次沉陷事故的冲击下,已无法确定完工时间1。
项目预算30亿澳元,已耗资27.8亿澳元1。该工程的完工日期经历过数次推延,从最初的2025年末顺延至2028年末,如今这一目标已被取消1。项目曾因一起10米宽的沉陷事故停工两年多,于6月份重启后,本周一在Rockdale路段再次出现2米宽洞穴,涉及最后244米路段1。政府已为该项目额外拨款2亿澳元1。尽管频频遭遇挫折,艾奇逊表示最新事故"绝对不会"导致进一步延误1。
NSW Roads Minister Jenny Aitchison acknowledged that the M6 underground motorway project in Sydney's south has no completion date, following repeated delays and construction complications 1. The four-kilometre tunnel, originally scheduled to open by the end of 2028, has already consumed AUD 27.8 billion of its AUD 30 billion budget 1. The project was first delayed from its initial target of late 2025, and Aitchison made the admission at a budget estimates committee hearing on Friday 1.
The motorway segment connecting Arncliffe to Kogarah has been plagued by construction difficulties. Work halted for over two years following a 10-metre-wide sinkhole that appeared in June, resuming only after the disruption was addressed 1. A fresh complication emerged this week when a two-metre cavity developed at Rockdale, affecting the final 244 metres of the route 1. Tensions between the contractor and government have contributed to the extended setbacks 1. Despite the latest incident, Aitchison stated it would "absolutely not" cause further delays 1. The government has already allocated an additional AUD 200 million to the project 1.
评论
还没有评论,欢迎留下第一条。