澳大利亚新南威尔士州政府宣布投入2.25亿澳元,用于升级南部可再生能源区(South West REZ)的电网基础设施1。这一升级计划在耗资36亿澳元的Project EnergyConnect输电线项目完成仅数月后启动1,旨在提升电网容量以支持计划中的风能和太阳能项目1。
升级工程将由能源运营商Transgrid承担,主要内容包括将Dinawan变电站和Wagga Wagga输电线的容量从330千伏提升至500千伏1。根据计划,工程预计于2027年启动,耗时两年完成1。Transgrid已与澳大利亚能源监管机构(AER)签订项目发展契约1。
值得注意的是,Project EnergyConnect的最终成本达36亿澳元,较初期预算的23亿澳元超支56%1。
The New South Wales government has committed $225 million to upgrade energy infrastructure in the South West Renewable Energy Zone, mere months after completing the Project EnergyConnect transmission line 1. The upgrades are designed to increase grid capacity to support planned wind and solar projects in the region 1.
Transgrid will undertake the upgrade work, which includes boosting capacity at the Dinawan substation and the Wagga Wagga transmission line from 330 to 500 kilovolts 1. The project is expected to begin in 2027 and will take two years to complete 1. Transgrid has already entered into a project development agreement with the Australian Energy Regulator 1.
The new investment follows the completion of Project EnergyConnect, which reached a final cost of $3.6 billion, representing a 56 percent increase over its initial $2.3 billion budget 1.