北京二环路全面升级工程近日取得阶段性进展,由北京建工承建的西直门桥东至建国门桥北段主体工程完工 1。该项目于2024年7月启动,全长32.7公里的二环路在通车34年后迎来系统性改造 1。此次完工路段包含北京建工养护集团负责的5.12公里2标段(西直门桥东-雍和宫桥东)以及北京建工市政集团负责的5.6公里3标段(雍和宫桥东-建国门桥北),累计完成25.5万平方米的路面沥青摊铺工作 1。
在技术实施方面,工程团队采用移动转运车配合激光距离反馈控制进行高精度摊铺,并实施全范围应力吸收层整体摊铺工艺以解决混凝土板接缝病害 1。整个项目遵循“先北后南、先主后辅”的建设时序,率先实施的北半环主路全长15.4公里,起点为复兴门桥南,终点至建国门桥北 1。按照计划,北半环主路工程预计将于11月底前完工 1。
除路面修复外,此次升级还融合了花园城市与智慧城市建设理念 1。全线将完成38.1万平方米路面重新铺装,更换0.76万延米老旧桥梁防撞护栏,并优化调整16处出入口及信号系统 1。为了提升设施智能化水平,工程部署了包括前端感知设备在内的各类设备共310台,覆盖56处出入口、4处重点路段及22处公交站 1。此外,沿线还将增设13.5万延米一体化中央隔离花槽,并增挂9400组花箱 1。
The main construction work on the section of Beijing’s Second Ring Road stretching from east of Xizhimen Bridge to north of Jianguomen Bridge has been completed, marking a significant milestone in the city's comprehensive upgrade project. 1 The full-scale renovation of the 32.7-kilometer ring road, which has been operational for 34 years, began in July 2024 and is being executed under the principles of "north first, then south" and "main road first, then auxiliary roads." 1 The Second Contract Section (5.12 kilometers from east of Xizhimen Bridge to east of Yonghegong Bridge) was managed by Beijing Construction Engineering Maintenance Group, while the Third Contract Section (5.6 kilometers from east of Yonghegong Bridge to north of Jianguomen Bridge) was overseen by Beijing Construction Engineering Municipal Group. 1 These teams successfully laid 255,000 square meters of asphalt during this phase. 1
To address specific structural issues and enhance smart infrastructure, the project utilized advanced techniques such as laser-controlled distance feedback paving with mobile transfer vehicles and full-range stress absorption layer paving to resolve concrete plate joint diseases. 1 According to the schedule, the entire northern half-ring main road, spanning 15.4 kilometers from south of Fuxingmen Bridge to north of Jianguomen Bridge, is expected to be fully completed by the end of November. 1 Once finished, this segment will feature optimized adjustments to 16 entrances and exits along with their signal systems, significantly improving traffic flow and landscape aesthetics. 1 Future phases include repaving 381,000 square meters of the entire route and replacing 7,600 linear meters of old bridge collision barriers. 1 Additionally, the upgrade integrates "Garden City" and "Smart City" concepts by installing 135,000 linear meters of integrated central isolation flower troughs, adding 9,400 sets of flower boxes, and deploying 310 frontend sensing devices covering 56 entrances/exits, 4 key sections, and 22 bus stops. 1 Subsequent stages involving other sections of the Second Ring Road are planned for phased implementation in 2027. 1