在即将举行的澳大利亚维多利亚州选举中,数十亿澳元的高压输电线路项目已演变为关键的政治议题 1。反对派联盟党和单一民族党均承诺若当选将废除或暂停主要输电工程,以回应农村地区因强制征地、景观破坏以及对城市受益不均的不满而爆发的抗议活动 1。尽管多数民众支持能源转型,但反对者认为这些项目加剧了偏远地区面临的生活成本压力和服务缺失问题 1。
目前争议的两大核心项目分别为190公里的“西部可再生能源链接”(Western Renewables Link, WRL)和横跨维州与新南威尔士州各约240公里的VNI West 1。联盟党此前承诺暂停并审查维州的输电计划,并于8月改变立场,表示若胜选将取消VNI West项目 1。单一民族党则更进一步,承诺全面废除VNI West、WRL及其他主要输电项目 1。现任维州州长Ben Carroll在9月下令立即评估WRL的成本,但其工党政府仍致力于推进VNI West的建设 1。
州政府强调新建输电线路对于替代退役燃煤电厂和稳定电网至关重要 1。为缓解阻力,州政府向同意在其土地上架设电线的土地所有者提供每公里20万澳元的福利包及补偿款 1。然而,VNI West路线经过的两个行政区Gannawarra和Buloke拥有维州比例最高的路况糟糕的道路 1。
High-voltage transmission projects have become a central political battleground in the upcoming Victorian state election, as opposition parties pledge to cancel multibillion-dollar infrastructure plans amid rural protests 1. The Coalition has committed to suspending and reviewing the state’s transmission strategy, shifting its stance in August to promise the cancellation of the VNI West project if elected 1. Similarly, One Nation has vowed to scrap both VNI West and the Western Renewables Link (WRL), along with other major transmission initiatives 1. These political commitments respond to growing discontent among regional communities over compulsory land acquisition, landscape degradation, and perceived inequities regarding who benefits from the energy transition 1.
Despite broad public support for renewable energy—Victoria generated approximately 44 percent of its electricity from renewables last year—opponents argue that these projects exacerbate cost-of-living pressures and service shortages in remote areas 1. The two core contested projects are the 190-kilometer WRL and VNI West, which spans roughly 240 kilometers across both Victoria and New South Wales 1. To address community concerns, the state government offers landowners a $200,000 per kilometer welfare package and compensation if they agree to host power lines on their properties 1. However, critics highlight that the VNI West route passes through the Shires of Gannawarra and Buloke, local government areas that possess some of the worst road conditions in the state 1.
The Victorian Labor government maintains that new transmission infrastructure is essential for replacing retiring coal-fired power stations and ensuring grid stability 1. While Premier Ben Carroll ordered an immediate cost assessment of the WRL in September, his administration remains committed to constructing VNI West 1. This divergence between government priorities and opposition promises underscores how transmission line routing has evolved into a critical electoral issue, reflecting deeper tensions regarding the equitable distribution of renewable energy costs and benefits across urban and regional centers 1.