随着电网连接和新建涡轮机等待时间不断延长,部分AI数据中心开始采用改造后的退役喷气式发动机进行自发电,以此显著缩短建设周期 1。尽管这种方式的能源效率较低且污染更大,但Rystad Energy分析师Audun Martinsen表示:“一切为了尽快获得电力”,利用喷气式发动机可使数据中心在24个月内投入运行 1。这一趋势背后是严峻的电力基础设施限制,国际能源署数据显示,在北弗吉尼亚州接入100兆瓦电网需耗时约7年 1。与此同时,微软因当地公用事业公司称直到2030年代初才能提供足够电力,上月撤出了英国Loughton的Nscale数据中心锚定客户身份 1。
目前,多家主要AI企业已采取实际行动部署此类设备。xAI已在密西西比州孟菲斯的Colossus 2数据中心安装了8台由ProEnergy制造的改造喷气发动机,这些引擎基于GE波音飞机引擎改装而成 1。2025年,OpenAI在其位于德克萨斯州Abilene的首个Stargate站点也使用了燃气轮机 1。此外,Crusoe于4月订购了13台ProEnergy的改造单元,并在9月放弃了一项与Boom Supersonic价值12.5亿美元、购买29台天然气轮机的交易 1。特朗普政府正鼓励数据中心自行发电 1。
AI data center operators are increasingly deploying modified, retired jet engines for on-site power generation to bypass lengthy wait times for grid connections and new turbine installations. Rystad Energy analyst Audun Martinsen stated that the primary motivation is speed, noting that using these jet-derived engines allows facilities to become operational within 24 months 1. This shift highlights a severe bottleneck in AI infrastructure development, where traditional energy procurement timelines are no longer viable for companies aiming to scale computing capacity rapidly 1.
The urgency stems from stark disparities in access to electricity. International Energy Agency data indicates that connecting 100 megawatts of load to the grid in Northern Virginia takes approximately seven years 1. In response to such delays, xAI has installed eight retrofitted GE Boeing aircraft engines manufactured by ProEnergy at its Colossus 2 facility in Memphis, Tennessee 1. Similarly, OpenAI utilized gas turbines at its first Stargate site in Abilene, Texas, in 2025 1. Crusoe also placed an order for 13 ProEnergy retrofit units in April and subsequently abandoned a $1.25 billion deal with Boom Supersonic for 29 natural gas turbines in September 1. These moves align with the Trump administration’s encouragement for data centers to generate their own power 1.
While repurposing aviation engines accelerates deployment, it comes with significant trade-offs regarding efficiency and environmental impact. The practice involves lower efficiency and higher pollution compared to standard power solutions 1. The severity of the power shortage was further illustrated last month when Microsoft withdrew as the anchor tenant for Nscale’s data center project in Loughton, United Kingdom, after local utilities indicated they could not provide sufficient electricity until the early 2030s 1.