Crusoe Energy与Boom Supersonic宣布终止一项能源供应合作协议。1根据协议,Crusoe原计划购买29台Boom Superpower涡轮机,单台功率42兆瓦,用于其位于美国德克萨斯州Abilene的数据中心园区,合同总额达12.5亿美元。1这些涡轮机原定于2027年开始交付。1
Boom首席执行官Blake Scholl表示,涡轮机不再是Crusoe近期Abilene等地的主要电力组合的一部分,双方因此决定终止合作。1尽管合作告吹,Boom仍在推进其商业化计划,目标在2025年交付约250兆瓦的Superpower涡轮机,并争取在2028年达到1吉瓦的交付规模。1
Crusoe Energy and Boom Supersonic have terminated a $1.25 billion turbine procurement agreement.1 Under the original deal, Crusoe had committed to purchasing 29 of Boom's 42-megawatt Superpower turbines for its Abilene data center campus in Texas, with deliveries scheduled to begin in 2027.1
Boom CEO Blake Scholl stated that turbines are no longer part of Crusoe's near-term power solution for Abilene and other locations, leading both companies to discontinue the partnership.1 The decision reflects a reassessment by Crusoe, which has raised $3.9 billion in funding, of its energy infrastructure requirements for powering its AI operations.1
Boom maintains its broader commercialization timeline, targeting delivery of approximately 250 megawatts of Superpower turbines in 2025 and aiming for 1 gigawatt by 2028.1 The company has secured $300 million in funding to advance its turbine technology.1