甲骨文公司已向其新墨西哥州数据中心项目的开发者发出不可抗力通知89。该项目名为"木星计划"(Project Jupiter),是一项AI数据中心开发347。甲骨文此举意在保护自身免于在设施未能按2028年目标上线时承担支付义务9。
该项目面临多重挑战。能源供应延迟构成主要障碍,天然气管道许可遭多次拒绝,Energy Transfer管道的交付时间已推迟至2027年2月1日9。此外,该项目还遭遇当地反对和实施困难7。新墨西哥州环境部面临11月23日的截止期限做出空气质量许可决定9。校园设计容量为2.45吉瓦9。
甲骨文表示项目仍按计划推进9,开发者Blue Owl Capital则声称该通知并不改变其对这一多年期项目的财务承诺9。然而市场对这一举措反应消极。甲骨文股价因此下跌,不同报道显示跌幅在4%至7%之间34678。相关项目贷款在二级市场的交易价格已跌至90美分345,反映了投资者对项目前景的担忧。
Oracle has sent a force majeure notice to the developers of its Project Jupiter data center in New Mexico, citing obstacles that may prevent the facility from meeting its 2028 target launch date.89 The company, which has committed to the facility with developer Blue Owl Capital, issued the notice to allow for delayed payment obligations should construction delays occur.9
The project, designed with a capacity of 2.45 gigawatts, faces multiple challenges including energy infrastructure delays.9 An Energy Transfer natural gas pipeline critical to the facility's operations has been postponed to February 1, 2027, pushing back the energy supply timeline.9 Additionally, the New Mexico Environment Department faces a November 23 deadline to make a decision on air quality permitting for the campus.9
Despite the force majeure notice, Oracle stated that "Project Jupiter remains on our planned schedule,"9 and Blue Owl Capital emphasized that the notice "does not change the financial commitments to this multi-year project."9 The data center project involves approximately $180 billion in debt, with related project loans trading at 90 cents on the secondary market.345 Oracle's stock declined between 4 percent and 7 percent following the announcement.348